SH 26 Reconstruction
Welcome to Colleyville

TxDOT SH26 Project

Project Update December 4

Village Lane opening
Crews opened the Village Lane intersection on Monday, Dec. 4

Pleasant Run Road closure
TxDOT plans the closure of the Pleasant Run Road intersection for Tuesday, Dec. 5. Motorists can detour on Village Lane or Main Street.

SH26 Pleasant Run Closure Map

Project Update November 28

Hall-Johnson Road work under flaggers
Work at this intersection will impact traffic from 9 a.m. to 3 p.m. on Wednesday, Nov. 29, and Thursday, Nov. 30, as concrete trucks and other equipment will need room without being impeded by traffic. Police and flaggers will be on-site but delays are expected and drivers should seek alternate routes.

Village Lane opening
TxDOT anticipates the opening of the Village Lane intersection on Monday, Dec. 4.

Pleasant Run Road closure
TxDOT is planning to close Pleasant Run Road at SH26 for necessary work after the opening of Village Lane, which is planned for Monday, Dec. 4. Motorists can detour on Village Lane or Main Street.

Project Update October 26

TxDOT will close Hardage Lane at SH26 on Nov. 7 as part of the SH26 Project. Motorists can detour on Tinker Road.

Project Update October 18

Tinker Road at SH26 is now open. The City and TxDOT thank the citizens, businesses, and motorists of Colleyville for their patience during this closure.   

Project Update October 6

Progress on Tinker Road at SH26 is evident. Asphalt has been laid, and today crews are placing forms for concrete paving, which is expected to begin next week. This intersection is expected to be fully re-open around mid-October. The City and TxDOT thank the citizens, businesses, and motorists of Colleyville for their patience during this closure.   

tinker road

Project Update September 29

village closure

Project Update September 27

Main Street at SH26 has been reopened. The contractor plans to fully close Village Lane at SH26 the week of October 2. Pleasant Run Road and Main Street will remain open while Village Lane is closed for reconstruction. 

Traffic shifts are expected at the intersections of Brown Trail and Centerpark Drive with SH26 Thursday and Friday, September 28 and 29. These shifts will put traffic on the new concrete and allow crews to construct the other half of the intersection leg. 

Project Update September 13

The contractor is expected to close the outside northbound lane of SH26, between Glade Road and Main Street on Thursday, September 14 beginning at 9:00 a.m. This will be a single lane closure and northbound motorists will be reduced to one-lane. The lane closure is expected to last continuously for approximately two-days to accommodate work, including excavation, and is necessary for the safety of motorists and workers. Business driveways in this area will remain accessible throughout the duration of the lane closure. 

NB Lane Closure

Reminder

SH26 Project Business Meeting 
Thursday, Sept. 7 at 9:00 a.m.
Colleyville Center, 5301 Riverwalk Drive

Meetings are intended to provide a time for members of the Colleyville business community to receive the latest project information, network, and for general inquiries. Staff will provide a brief update on the project, take questions, and work one-on-one with attendees to address site/property questions. 

Project Update August 25

Main Street at SH26: expected to fully reconstructed and reopened in approximately 4-weeks. 

Tinker Road at SH26: expected to be fully reconstructed and reopened in approximately 4-weeks.  

The closure of Tinker at SH26 is expected to last approximately 4 more weeks in part due to the complexity of the drainage infrastructure being constructed underneath the intersection. The closure will allow the contractor to complete the full reconstruction of the west side of the intersection prior to reopening. The highlighted portions of the graphic below indicate the new storm drain infrastructure being installed at Tinker Road. Recent rain events have made work difficult in this area because crews have to ensure positive drainage is maintained throughout the construction process.   

Tinker

Project Update August 24

The traffic signals at Brown Trail/SH26 are expected to be out of service today (in all directions), August 24, from approximately 9 a.m. to 11 a.m., as Oncor Electric makes required adjustments at the intersection. Colleyville Police will be on-site to direct traffic. 

Project Update August 18

Main Street at SH26: expected to reopen in approximately 5-weeks.

Tinker Road at SH26: several factors have led to the closure of Tinker Road lasting longer than expected. TxDOT and the contractor are currently evaluating options to complete the reconstruction on the west side of the intersection in a single step, as opposed to a brief temporary re-opening, followed by another closure for concrete paving. At this time, it is expected this closure will last at least another 4-weeks.  

With school starting next week there will be an increase in traffic congestion.  Please allow additional travel time to assist in getting to your destination on time.

TxDOT and the City appreciate the patience of motorists and encourages attention to all warning signs within the construction work zone. 

Project Update August 11

Rolling single lane closures are expected to take place on Wednesday, August 16 beginning at 7 a.m. (this was rescheduled due to rain) throughout the construction zone. The closures will begin on the southbound side of SH26 and transition to the northbound lanes later in the day. The rolling closures will accommodate the delivery of additional concrete traffic barriers.

Permanent concrete paving operations have begun. This week concrete pours were performed in the area of the future northbound lanes south of Brown Trail, and at the Centerpark Drive intersection. Concrete paving operations will continue along the corridor for the next few months. Storm drain installation and subgrade stabilization continues throughout the corridor.

Concrete paving

Project Update July 28

Motorists can expect to see progress on the bridge over Little Bear Creek to include concrete slab pours. Additional work throughout the corridor will include right-of-way preparation, storm pipe installation, and subgrade stabilization.

The closure on Tinker Road at the intersection is extended through this week as the contractor is working extra cautiously with safety in mind. Motorists are encouraged to detour on Hardage Lane and Ponderosa Street.

Project Update July 19

Week of July 23: Motorists can expect to see progress on the bridge over Little Bear Creek to include concrete slab pours. Additional work throughout the corridor will include right-of-way preparation, storm pipe installation, and subgrade stabilization.

Tinker Road remains closed. The City is working with TxDOT to obtain further information. - updated Aug. 11

Tinker Road Closure Exhibit

Project Information July 17

The contractor is preparing to lay asphalt at the intersections of Centerpark Drive and Brown Trail with SH26. As reflected in the exhibit below, asphalt is part of the stabilization process for the new highway. The final road surface will be constructed of 10-inches of continuously steel reinforced concrete.  

Paving Exhibit

Project Update July 14

Week of July 16: Motorists can expect construction activity on the east side of SH26 south of Centerpark Drive which will include bridge slab work near Little Bear Creek Bridge and stabilization and asphalt work near Brown Trail and Centerpark Drive. Construction activity throughout the rest of the corridor will include preparation of ROW and stabilization on the west side of SH26 between Centerpark Drive and John McCain Road and storm drain installation north of Glade Road to Hall-Johnson Road. Lane closures throughout the project limits are possible from 9:00 a.m. to 3:00 p.m. (weather permitting) and SH26 could be reduced to one lane at times, possibly causing delays.

 

Project Update July 6

***Village Lane has been reopened as of 12:40 p.m., Thursday, July 6***

Village Lane at SH26 is temporarily closed due to a low-hanging utility line caused by the overnight storm. Utility companies are being contacted to address the issue. Pleasant Run Road remains open from SH26. 

Utility Line Across Village Lane

 

Project Update July 3

***This has been rescheduled for Friday, July 7, due to weather***

As currently scheduled, on Wednesday, July 5, from 7:00 a.m. to 7:00 p.m. the southbound outside lane of State Highway 26 will be closed from Mission Lane to Village Lane as crews work near the edge of the road. This closure is necessary for the safety of motorists and workers. The inside southbound lane of SH26 should remain open during this time.    

SH26 southbound closure map

 

 

Project Update June 21 

SH26 Project coordinator James Hubbard presented a quarterly updated to the City Council at the June 20 meeting. Watch the update below.

UPDATE

TxDOT has reopened both southbound lanes on SH26 near Main Street. Thank you for your patience as crews worked to address this issue. (June 20, 1:42 p.m.)


 

Southbound SH26 has been reduced to one lane near Main Street due to a road surface failure. Lane closure expected to last through the evening rush hour. More information will be posted as it becomes available. (June 20, 10:34 a.m.)

Road Failure

Project Update June 16

Per the exhibit below, Main Street at SH26 is expected to be closed beginning Monday, June 19 for reconstruction. Detour signs will be present along SH26. Lanes at Tennison Parkway and Tuscany Drive are also expected to shift the week of June 19, per the exhibit below. More information regarding the duration of the Main Street closure and lane changes will be posted as it is available.

Main Street Closure

Traffic Shift

 

Attention

Lanes on Church Street at the SH26 intersection are expected to change Tuesday, June 6. Traffic on the west side of SH26 will be reduced to two lanes. Motorists heading westbound on Church Street will be required to turn right from the right lane.

Church Street

Attention

Lane assignments on Glade Road at the SH26 intersection have shifted. Traffic on the west side of SH26 is now reduced to two lanes. Motorists heading westbound on Glade Road must turn right from the right lane.  

Glade Road

 

Project Update May 30

Motorists can expect to see increased activity at the intersections of SH26 with Glade Road, Church Street, and Hall-Johnson Road beginning tomorrow (5/31). Lanes on the west side of SH26 at these intersections will be reduced to create a construction zone. Motorists will be able to travels in all directions, but may encounter delays.

Project Update May 19

Motorists can expect to see construction activity south of Glade Road including storm drain installation and bridge work near Little Bear Creek. Additional activity throughout the rest of the construction zone will include placement of traffic control devices and concrete traffic barrier (CTB), excavation on the west side of SH26 between Centerpark Drive and John McCain Road, and temporary detour construction on side streets at Glade Road and Main Street.

Lane closures throughout the project limits are possible from 9 a.m. to 3 p.m. (weather permitting) and SH26 could be reduced to one lane in each direction at times, possibly causing delays. Message boards are posted advising motorists of upcoming daily lane closures. 

Project Update May 15

The traffic signals at the intersection of SH26 and Centerpark Drive are currently flashing red. Signal technicians have been notified. Delays are expected through the evening rush hour.

Reminder

There is a SH26 Business Meeting this Thursday, May 4 at the Colleyville Center, 5301 Riverwalk Drive. The meeting will start at 9:00 a.m. and include a project update and time to visit with City and TxDOT representatives. The meeting is intended for businesses along, or near, State Highway 26. We hope to see you there.  

Project Update April 26

Attention

Attention
 
Continuous center turn lanes have been removed.
 
The removal is being conducted in conjunction with traffic shifts to create a work zone. 
 
TxDOT asks motorists to keep the following tips in mind when driving through work zones:

• Slow down and always follow posted work zone speed limits. Speeding is one of the major causes of work zone crashes. 
 
• Pay attention. Workers and heavy equipment may only be a few feet from passing vehicles.
 
• Don’t tailgate.
 
• Stay alert and minimize distractions such as cell phones
 
• Obey road crew flaggers
 
• Expect the unexpected. Delays from highway construction can be frustrating, but it only takes a few extra minutes to slow down for a work zone.
 
• Plan ahead. Leave a few minutes early when traveling through a work zone to reach your destination on time.

Project Update April 24

Traffic shifts are scheduled for Wednesday, April 26 and Thursday, April 27 (see limits below), weather permitting. Travel lanes will be moved to the east side of SH26, the continuous left-turn lane will be removed, and the Phase 1 construction area will be located on the west side of SH26 within these limits (see graphic below). Police will be on-site to assist with traffic control during the traffic switch and motorists can expect delays during this activity.

Wednesday, April 26: Glade Road to Church Street

Thursday, April 27: Church Street to Tinker Road

Once traffic shifts have been completed for Phase 1, daily lane closures should be limited for the remainder of Phase 1 construction.

Phase 1 - Traffic Control Plan

 

Project Update April 19

A traffic shift is scheduled for Friday, April 21 between Centerpark Drive and Mission Lane (weather permitting). Travel lanes will be moved to the east side of SH26, the continuous left-turn lane will be removed, and the Phase 1 construction area will be located on the west side of SH26 within these limits (see graphic below). Police will be on-site to assist with traffic control during the traffic switch and motorists can expect delays during this activity.

Traffic shifts from Mission Lane to John McCain Road are pending in the near future with more information to be posted soon. Once all traffic shifts have been completed for Phase 1, daily lane closures should be limited for the remainder of Phase 1 construction.

Project Update April 18

There will be increased construction activity and temporary lane closures at the Brown Trail intersection beginning Wednesday, April 19. Motorists will be able to travel in all directions, but should expect delays. 

Project Update April 17

Thompson Terrace is currently closed at State Highway 26. The intersection is expected to reopen later this afternoon (4/17). Businesses on Thompson Terrace may be accessed from Glade Road. 

Project Update April 12

Partial Closure of Church Street - April 14

 

Project Update April 7

The activation of temporary traffic signals is expected to take place at two intersections the week of April 10:

Monday, April 10 - Hall-Johnson Road

Thursday, April 13 - Tinker Road 

This activity will involve the removal of existing traffic signals/masts and the activation of temporary traffic signals, which will remain during the reconstruction of the highway. Motorists can expect delays and lane closures due to this activity. Police will be on-site to assist with traffic.

Additional construction activity throughout the rest of the corridor will include the placement of additional traffic control devices, driveway sawing and removal and installation of temporary pavement at various locations along the project limits. Lane closures throughout the project limits are possible from 9 a.m. to 3 p.m. (weather permitting) and SH26 could be reduced to one lane at times, possibly causing delays.  Message boards are posted advising motorists of upcoming daily lane closures. 

Project Update March 28

Various lane closures for the activation of temporary traffic signals to occur at the intersection of Church Street and SH26 on Wednesday, March 29, pending weather.

This activity will involve the removal of existing traffic signals/masts and the activation of temporary traffic signals, which will remain during the reconstruction of the highway. Motorists can expect delays and lane closures due to this activity. Police will be on-site to assist with traffic.

TxDOT appreciates the patience of motorists and encourages attention to all warning signs within the construction work zone while crews work to complete this project quickly and safely.

Project Update March 21

SH26 Project coordinator James Hubbard presented a quarterly updated to the City Council at the March 21 meeting. Watch the update below.

Project Update: March 10, 2017

The traffic shift scheduled for today has been completed. 

Traffic Shift 3_1_2017

The SH26 construction project has progressed to Phase 1 work.  Motorists can expect to see construction activity south of Glade Road including placement of concrete traffic barriers (CTB) and milling and removal of old pavement in the coming weeks.  Additional construction activity throughout the rest of the project will include the placement of the remaining temporary traffic signals, more traffic control devices and installation of temporary pavement at various locations along the project limits. Lane closures throughout the project limits are possible from 9 a.m. to 3 p.m. (weather permitting) and SH26 could be reduced to one lane at times. Message boards are posted advising motorists of upcoming daily lane closures. 

TxDOT Update: March 9, 2017

Weather permitting, a traffic shift is now planned to occur on Friday, March 10, for north and southbound traffic south of Glade Road. The new traffic pattern will eliminate the continuous left-turn lane in this area.

TxDOT appreciates the patience of motorists and encourages attention to all warning signs within the construction zone while crews work to complete this work.

TxDOT Update: March 3, 2017

 

Signal Work and Traffic Shift Scheduled for Week of March 6

 

Motorists can expect delays and lane closures due to upcoming traffic signal work and a traffic shift south of Glade Road. Below is an estimated schedule for the upcoming work (schedule is subject to change).

 

Monday and Tuesday (March 6 and 7, 9 a.m. - 3 p.m.)

 

  • Installation of temporary pavement and pavement markings south of Glade Road along with other construction throughout the corridor

 

Wednesday (March 8, 9 a.m. - 3 p.m.)

 

  • Activation of temporary traffic signals at Glade Road
  • Traffic Shift- southbound motorists will be shifted onto the temporary paving south of Glade Road 

 

Thursday (March 9, 9 a.m. - 3 p.m.)

 

  • Activation of temporary traffic signals at Main Street and Mission Lane
  • Traffic Shift - northbound motorists will be shifted south of Glade Road

 

TxDOT appreciates the patience of motorists, and encourages attention to all warning signs within the construction work zone while crews work diligently to complete this work as quickly and as safely as possible.

TxDOT Update: March 2, 2017

Throughout the project, to accommodate construction, protected left turns (left on green arrow only) will be implemented and signed at some intersections between Brown Trail and Tinker Road. The use of the protected left turns will provide increased safety within the construction limits by making traffic movements more predictable. Furthermore, temporary traffic signals will be equipped with radar detection to provide more reliable vehicle detection at intersections, even in adverse weather and low light conditions.  The same radar detection technology will be used in the permanent signals along with the reinstallation of permitted left turns (left on flashing yellow arrow allowed) at most locations when the project is complete.

TxDOT Update: February 22, 2017

The activation of the temporary traffic signals at the Centerpark Drive intersection is complete.

Centerpark Temp Signals

Various lane closures for traffic signal work to occur at Brown Trail/Mill Valley Drive at SH26 (subject to weather):

Work is expected to begin Thursday, Feb. 22, and be completed early next week. Crews will work daily from 9:00 a.m. to 3:00 p.m., possibly including weekend work (crews will remain on-site until work is completed).

This activity will involve the removal of existing traffic signals/masts and the placement of temporary traffic signals, which will remain during the reconstruction of the roadway. Motorists can expect delays and lane closures due to this activity and should seek alternate routes during this time. Police will be on-site to assist with traffic.

TxDOT appreciates the patience of motorists and encourages attention to all warning signs within the construction work zone while crews work to complete this project quickly and safely.

TxDOT Update: February 20, 2017

Expect Delays

Various lane closures for traffic signal work to occur at Centerpark Drive at SH26 (subject to weather):

Work is expected to begin Tuesday, Feb. 21 and will take a minimum of two days to complete, 9:00 a.m. to 3:00 p.m. (Crews will remain on-site until work is completed)

This activity will involve the removal of existing traffic signals/masts and the placement of temporary traffic signals, which will remain during the reconstruction of the roadway. Motorists can expect delays and lane closures due to this activity and should seek alternate routes during this time. Police will be on-site to assist with traffic. Upon completion of this work, the contractor is expected to begin work on the traffic signals at Brown Trail. More details to be posted soon.

TxDOT appreciates the patience of motorists and encourages attention to all warning signs within the construction work zone while crews work to complete this project quickly and safely.

TxDOT Update: February 14, 2017

Over the next several days the contractor will be addressing temporary driveways affected by the recent rain. 

TxDOT Update: February 10, 2017

On Saturday, February 11, the contractor is expected to work throughout the corridor. Lane closures are anticipated and are not restricted by peak hours.

The SH26 construction project continues with preliminary work. Motorists can expect to see construction activity continue including placement of more traffic control devices and erosion control measures, surveying crews, and installation of drainage. Motorists can also expect to see the installation of temporary pavement and temporary driveways at various locations along the project limits. Lane closures throughout the project limits are possible from 9:00 a.m. to 3:00 p.m., and SH26 could be reduced to one lane at times, weather permitting. Message boards are posted advising motorists of upcoming daily lane closures.

TxDOT Update: February 9, 2017

Northbound lane closure near Tinker Road expected to last until approximately 3:45 p.m. this afternoon. Please expect delays.

TxDOT Update: February 8, 2017

Northbound lane closure near Church Street expected to last until approximately 3:45 p.m. this afternoon. Please expect delays. 

TxDOT Update: February 6, 2017

The SH26 construction project continues with preliminary work. Motorists can expect to see construction activity continue including placement of more traffic control devices and erosion control measures, surveying crews, and installation of drainage. Motorists can also expect to see the installation of temporary pavement and temporary driveways at various locations along the project limits. Lane closures throughout the project limits are possible from 9:00 a.m. to 3:00 p.m., and SH26 could be reduced to one lane at times, weather permitting. Message boards are posted advising motorists of upcoming daily lane closures. 

TxDOT Update: January 30, 2017

Due to some construction issues, TxDOT will reschedule the traffic signal work on SH26 at Brown Trail and Centerpark Drive originally scheduled for today (1/30) and tomorrow (1/31). Notice of the upcoming work will be sent after it has been rescheduled.

We thank motorists for their continued patience during this project.

TxDOT Update: January 29, 2017

Due to an unexpected issue, the intersection of Brown Trail and SH26 is currently operating as a four-way stop. This will continue until police arrive on-site tomorrow (1/30) at 7:00 a.m. to direct morning rush hour traffic. 
 
The work planned at this intersection (see below update) is still planned to occur on 1/30 beginning at 9:00 a.m. 

TxDOT Update: January 27, 2017

Expect Delays

Various lane closures for traffic signal activation to occur at the following locations/days (subject to weather):

  • Brown Trail/Mill Valley at SH26 

           Monday, Jan. 30 from 9 a.m. to 3 p.m.*

  • Centerpark Drive at SH26

           Tuesday, Jan. 31 from 9 a.m. to 3 p.m.*

                                                                          *crews will remain on-site until work is completed

Motorists can expect delays and lane closures due to this activity and should seek alternate routes during this time. Police will be on-site to assist with traffic.

This activity will involve the removal of existing traffic signals/masts and place temporary traffic signals which will remain during the reconstruction of the roadway.

TxDOT appreciates the patience of motorists, and encourages attention to all warning signs within the construction work zone while crews work diligently to complete this work as quickly and as safely as possible.

TxDOT Update: January 25, 2017

The contractor is expected to perform overhead signal work at the intersection of Tinker Road and State Highway 26 today. This work may result in the closure of Tinker Road for a short period of approximately 15 minutes. Colleyville Police will be on-site to direct traffic. 

TxDOT Update: January 13, 2017

The SH 26 construction project continues with preliminary work. Motorists can expect to see construction activity continue including placement of more traffic control devices and erosion control measures, installation of temporary traffic signals, surveying crews, tree removal and installation of drainage. Motorists can also expect to see the installation of temporary pavement and temporary driveways at various locations along the project limits. Lane closures throughout the project limits are possible from 9 a.m. to 3 p.m., and SH 26 could be reduced to one lane at times, weather permitting. Message boards are posted advising motorists of upcoming daily lane closures.

For project information and to stay informed, sign-up for e-mail alerts on construction activity, log on to: SH26Project.com

TxDOT Update: January 3, 2017

TxDOT has informed the City that the today’s northbound single lane closure on SH26 near the Hall-Johnson intersection will extend to 4:00 p.m. today due to an unexpected contractor delay.

TxDOT Update: December 30, 2016

Crews will suspend activity over the holiday weekend, with work resuming on January 2.

Preliminary work will continue in January to include the installation of temporary paving as seen below near the Sonic Drive-in restaurant. Activity will also include work on temporary traffic signals, storm drainage, and tempoprary driveways. 

SH26 Temporary Paving

TxDOT Update: December 22, 2016

Crews working on SH26 will suspend activity through the holidays from Thursday, Dec. 22, to Wednesday, Dec. 28. This break will allow drivers to travel the corridor and shoppers and diners to reach local businesses without lane closures during the holiday.

So far in TxDOT’s project, crews have conducted preliminary work including installing traffic control devices, temporary pavement, erosion control measures, and more.

TxDOT Update: December 16, 2016

The SH26 construction project continues with preliminary work. Motorists can expect to see construction activity continue including placement of more traffic control devices and erosion control measures, installation of temporary traffic signals, surveying crews, tree removal and installation of drainage. Motorists can also expect to see the installation of temporary pavement and temporary driveways at various locations. Lane closures throughout the project limits are possible from 9 a.m. to 3 p.m., and SH26 could be reduced to one lane at times, weather permitting.  Message boards are posted advising motorists of upcoming daily lane closures. SH26 construction activities will be suspended over the holidays beginning December 22 thru December 28.

TxDOT Update: December 9, 2016

Thank you

Construction activity over the coming weeks will include the placement of more traffic control devices and erosion control measures, installation of temporary traffic signals, surveying crews, tree removal and installation of drainage infrastructure. Motorists can also expect to see the installation of temporary pavement and temporary driveways at various locations. Lane closures throughout the project limits are possible from 9 a.m. to 3 p.m., and SH26 could be reduced to one lane in each direction at times, weather permitting. 

To minimize the impact to traffic around Christmas the contractor does not plan to work December 22-28. 

TxDOT Update: November 23

Motorists can expect to see construction activity continue over the coming weeks including placement of traffic control devices and erosion control measures, installation of temporary traffic signals, surveying crews, tree removal and installation of drainage. Various lane closures are possible from 9 a.m. to 3 p.m., and SH 26 could be reduced to one lane, weather permitting. Motorists can also expect to see the installation of temporary driveways at various locations. 

TxDOT Update: November 18

The SH 26 construction project continues. Motorists can expect to see construction activity continue over the coming weeks including placement of traffic control devices and erosion control measures, installation of temporary traffic signals, surveying crews, tree removal and installation of drainage. Various lane closures are possible from 9 a.m. to 3 p.m., and SH26 could be reduced to one lane in each direction, weather permitting. Motorists can also expect to see the installation of temporary driveways at various locations.

Construction will be suspended next week from Nov. 23-25 in observance of the Thanksgiving Holiday season.

Project Update: November 14

A subcontractor working on utility relocations along SH26 has hit a gas line at the Hall-Johnson Road intersection. A southbound lane of traffic is closed and Atmos is on-site. Drivers should expect delays. Officials expect repairs to last through the evening.

TxDOT Update: November 11

In addition to the activities listed in the update immediately below, TxDOT plans to close various commercial driveways for construction activity over the following weeks. Access will be maintained to all properties via alternate access points. The City and TxDOT are working to communicate the details of these closures with the affected properties. 

TxDOT Update: November 8

The SH26 contractor is planning to have a daily lane closure along the corridor at Brown Trail and another near John McCain Road, weather permitting. Crews will install temporary signals and conduct tree removal. City staff is actively marking trees that will be protected as outlined in TxDOT plans. The lane closures will be restricted from 9:00 a.m. to 3:00 p.m.

TxDOT Update: November 4

The SH26 construction project will begin next week. Message boards have been placed within the corridor to announce the start. Motorists can expect to see construction activity over the coming weeks including placement of traffic control devices and erosion control measures, installation of temporary traffic signals, surveying crews, tree removal and installation of storm drainage. Various lane closures are possible from 9:00 a.m. to 3:00 p.m., weather permitting.

TxDOT Update: SH 26 Construction to Begin in Colleyville

Beginning this month, the Texas Department of Transportation (TxDOT) will start the $38.2 million State Highway 26 reconstruction project in Colleyville from John McCain Road to Brown Trail. The 3-mile project, which will improve mobility and safety, will consist of the widening SH26 from four lanes with a continuous left turn lane to six lanes with raised curb medians with left turn bays, continuous sidewalks and improved signals. The project was awarded to Jagoe-Public Company of Denton, and is estimated for completion in 2019.

During the majority of construction, two lanes of traffic will be maintained in each direction. Closures will be during off-peak travel times to minimize impact to motorists. The project includes financial incentives for early completion.

Motorists can view information on closures at drivetexas.org.

Safety is a top priority at TxDOT, and the foundation for the agency’s planning, building and maintaining of projects across the state. When driving through a work zone, some simple steps to take are: slow down, pay attention, avoid distractions such as cell phones, be patient and plan ahead.

TxDOT SH26 Project Update - October 31, 2016

The Texas Department of Transportation informed the City of Colleyville that it plans to begin construction along State Highway 26 the week of Nov. 7.

Crews will place electronic message boards regarding the project along the roadway today, Mon., Oct. 31. The message boards will alert drivers to the project’s start date and to expect delays along the corridor.

This TxDOT project will expand SH26 to three lanes in both directions with raised medians and left-turn lanes. The City is working closely with TxDOT and the project contractor and will provide updates throughout the project.

To stay updated sign up for text alerts by texting “SH26” to 48421, or sign up for email alerts online at SH26Project.com.

TxDOT SH26 Project Update - August 26, 2016

The Texas Department of Transportation (TxDOT) provided a SH26 project update for August 2016 and reported that utility companies continue to make progress moving utilities. Relocation of the utilities should be completed this fall, with construction starting soon after.

While the project had the potential to begin as early as summer, work to expand the roadway to six lanes is not slated to begin until utility relocation is complete. Companies have brought in additional crews to expedite the completion of this process.

Supporting the community throughout the project’s duration remains one of Colleyville City Council’s top priorities. City staff meets regularly with project stakeholders including local businesses, TxDOT, and the project contractor Jagoe-Public. The city was responsible for managing the relocation of water and wastewater utilities along the corridor. Work to complete this portion of the utility relocation was completed in the fall of 2015.

_______________________________________________________

 

TxDOT SH 26 Project Update - April 19, 2016

City staff presented an update on TxDOT’s SH26 project at the April 19 City Council meeting. The presentation gave an overview of the project's current state, the city’s initiatives to communicate and keep the community updated, and what is next for the project.

The bid for the project occurred on Feb. 10, 2016, with the low bid at a total of $38,223,663. James Hubbard, the State Highway 26 Project Coordinator, touched on the on-going communication efforts with residences, businesses, property owners, HOAs, the school district, and various clubs and organizations. He also showcased the now available text and email alerts.

The next steps for this project include the consideration of two Advance Funding Agreements presented at a future City Council meeting. 

A recording of the presentation to City Council is available here; the item is listed as PC-2.

______________________________________________

TxDOT SH26 Project Update - Feb. 5, 2016

The Texas Department of Transportation (TxDOT) has signed off on the completion of Phase I construction from the northern city limits to John McCain Road and is nearing the start of the next phase.

Phase II will be the largest road project in Colleyville history and includes a new six-lane roadway with a center turn lane and raised medians, and drainage system improvements along the city’s main commercial corridor. It features approximately 23 lane miles of new roadway, approximately 4.8 miles of 8-foot-wide sidewalks, eight signalized intersections, and a bridge over Little Bear Creek. TxDOT estimates the project cost at approximately $33.5 million.

TxDOT has advertised the project and a bid opening has been set for Feb. 10. Unlike Phase I, the city was able to work with TxDOT to have incentives and liquidated damages terms added to the Phase II contract. These terms are tied to four milestones spread throughout the project’s duration, allowing for four separate opportunities for TxDOT to assess the contractor, which is intended to keep the contractor on schedule.

The construction plan includes a traffic control plan to guide work that has the least impact on drivers. The traffic plan’s main goal is to maintain four lanes of traffic, with the exception of temporary lane closures. Single-lane closures will be limited to off-peak hours, which means no single-lane closures from 6:00-9:00 a.m. and 3:00-7:00 p.m., Monday through Friday. Work that requires multiple lane closures in the same direction will be limited from 9:00 p.m. to 6:00 a.m. or weekends.

Webcast [PC-3]

__________________________________________

TxDOT SH26 Project Update - Jan. 13, 2016

TxDOT has completed the SH26 Phase I reconstruction from Brumlow Avenue/Pool Road to John McCain Road is now complete. The speed limit will remain at 35 miles-per-hour at this portion of the roadway until a final inspection, according to TxDOT’s mobility coordinator. If there are no issues the work zone signs should be removed in a few weeks.

Phase I of the state project widened the roadway to three lanes in each direction with raised curb medians and left turn lanes.

The SH26 Phase II reconstruction project from John McCain Road to Brown Trail is planned to begin in Spring 2016. The 3-mile TxDOT project will widening the roadway to three lanes in each direction and includes raised curb medians.