Glade Road Project

Print
Press Enter to show all options, press Tab go to next option

Overview

Glade Road has been an integral part of Colleyville’s road system for many decades, and is an important east-west transportation route for residents, businesses and visitors. The road shares many features, which contribute to Colleyville’s hometown feel, including trees, scenic pastures, and rural stretches.Riverwalk Roundabout

Key features of the project include a roundabout at Riverwalk Drive and the City received grant funding to include the lowering of Bluebonnet Drive. During this phase of construction, the intersection will be closed to traffic.

Project Schedule

Glade Road (Colleyville Boulevard to Pool Road)

July 2019—Franchise utilities mobilized into the area to begin relocating utilities in the corridor

March 3, 2020—Bid Opening—Glade Road Phase 2 is currently out for bid

April—Council meeting to award construction contract

May—Public meeting to discuss the project and introduce the project team

July—Construction of Glade Road is anticipated to commence

Anticipate a 24-30 month construction timeline depending upon weather conditions