Atlas Resource (formerly Titan Operating, LLC) Drill Site - 7504 Pleasant Run Road

Contact Information

Questions regarding drilling and operation of gas wells may be directed to the Community Development Department at 817.503.1052, or by email to rruthven@colleyville.com.

 

Drill Site Timeline

March 2011 - Drilling of first well(s) commenced

August 2011 - First phase of drilling completed

 

Titan Drilling Application

Request for a Special Use Permit for a gas well site on 13.24 acres on Lot 1, Block1, of the Park
Place Estates Addition and Tract 1D, Abstract 295 in the W.E. Crooks Survey located at 7404 and 7504 Pleasant Run Road, Case ZC10-022 


Titan Operating LLC Application -
Briefing Nov. 3, 2010


Titan Presentation - Drill Site

Titan Presentation - Groundwater

Hydrologic and Hydraulic Report

Webcast of Nov. 3 Council Meeting 

Titan Operating LLC Application -
Briefing Nov. 16, 2010

 

 

Related Information 

Titan Special Use Permit 
Road Remediation and Repair
Seismic Survey Map
Total Seismic Survey Packet
Material Safety Data Sheets 
  w/Hydraulic Fracturing and Fluid Breakdowns
Preliminary Regional Pipeline Route

Tree Preservation Plan
Well Bore Drilling Routes/Lateral Maps
OSHA-Gas Well Drilling

Updates

Update: October 14, 2014

Stage five fracking is complete.  Stage six perforating is scheduled for mid-December and stage six fracking is scheduled for mid-March 2015

Previous updates

Pipeline Construction

Representatives from Access Midstream, a pipeline operator, informed City staff that they have signed a contract with Atlas Resource Partners, the operator of the gas well site at 7504 Pleasant Run Road (known as the Trinity Unit on Railroad Commission License), for the survey and design of a gas well pipeline (phase one). Read more


Permits

General Administrative Permits

Grading and Hydrology Permits

 

 

Inspection Summary Reports

Inspection Reports - Phase One Drilling
View all inspection reports

Inspection Reports - Phase One Fracking
View all inspection reports

Inspection Reports - Phase Two Fracking
View all inspection reports

NOISE
Noise Mitigation Plan - Final

AIR QUALITY
Baseline Air Quality Assessment - February 2011

Final Air Quality Analysis Summary - Phase One Hydraulic Fracturing and Flowback Operations

Final Air Quality Analysis Summary - Phase Two Hydraulic Fracturing

WATER
Colleyville Water Baseline Report - 2012

Baseline Water Quality Assessment - March 2011

 


 

 

 





 

 

 

 



 

City of Colleyville | 100 Main Street, Colleyville, Texas 76034 | 817-503-1000 | Contact the city