City Projects: Street Improvements - Pleasant Run Road and John McCain Road Intersection Improvements

Street Improvements
Pleasant Run Road and John McCain Road
Intersection Improvements
 
Pleasant Run and John McCain 
 

Key Information

  • Promote a safe intersection for both vehicular and pedestrian traffic
  • Provide an intersection that will meet future traffic needs

Current Activity (as of September 2011)

  • Design by Burgess and Niple is currently 99% complete
  • Right-of-way acquisition currently underway
Funding
  • Project budget: $1,312,000
  • Funding sources:
  • Service Area II Impact Fees ($475,099)
  • Water Impact Fees ($148,490)
  • Tarrant County Bond Funds ($201,359)
  • Capital Projects Street Resurfacing Funds Transfer ($587,052)

 Key Dates

  • Preliminary study completed: March 15, 2010
  • Public meeting: May 6, 2010
  • City Council award of design contract to Burgess and Niple: July 16, 2010
  • Design completion: March 2011
  • Construction estimated to take 6 months once initiated

 Staff Contact

 
City of Colleyville | 100 Main Street, Colleyville, Texas 76034 | 817-503-1000 | Contact the city