City Projects: Street Improvements - Pleasant Run Road and John McCain Road Intersection Improvements
Street Improvements
Pleasant Run Road and John McCain Road
Intersection Improvements
Key Information
- Promote a safe intersection for both vehicular and pedestrian traffic
- Provide an intersection that will meet future traffic needs
Current Activity (as of September 2011)
- Design by Burgess and Niple is currently 99% complete
- Right-of-way acquisition currently underway
Funding- Project budget: $1,312,000
- Funding sources:
- Service Area II Impact Fees ($475,099)
- Water Impact Fees ($148,490)
- Tarrant County Bond Funds ($201,359)
- Capital Projects Street Resurfacing Funds Transfer ($587,052)
Key Dates
- Preliminary study completed: March 15, 2010
- Public meeting: May 6, 2010
- City Council award of design contract to Burgess and Niple: July 16, 2010
- Design completion: March 2011
- Construction estimated to take 6 months once initiated