City Projects: Sidewalk/Trail Improvements - Cotton Belt Trail Phase II - L.D. Lockett Trail
Sidewalk/Trail Improvements
Cotton Belt Trail Phase II - L.D. Lockett Trail
Key Information
- Provides connectivity with existing Cotton Belt Trails in Hurst and North Richland Hills
- Provides connectivity at L.D. Lockett Park to the Cotton Belt Trail
Current Activity (as of January 2012)
- Construction complete within Colleyville and Hurst
Funding
- Project budget: $1,010,270
- Funding sources:
- FY 2011 Colleyville Economic Development Corporation Budget ($100,000)
- Park Land Dedication Fund ($162,670)
- TxDOT Grant ($747,600)
Key Dates
- City Council award of contract to Humphrey and Morton: August 17, 2010
- Construction began: November 29, 2010
- Colleyville and Hurst section: Open