| Road Construction Updates |
|
Glade Road: Crews are working on brick pavers in the medians, irrigation, landscaping and cleanup. Substantial completion is expected by the end of May 2008. Church Street (Phase 1-east half): Substantially complete. Phase 2 (west half) is closed to through traffic during construction. Drainage structures are nearing completion. Crews are currently working on utility improvements. Completion anticipated by mid-July 2008. Bogart Drive: Construction is set to begin by the end of May. Improvements include new concrete pavement from Pleasant Run to Hall-Johnson, water line replacement, drainage structures, 10’ trail, and a round-a-bout at the intersection with Hall-Johnson. Completion is anticipated by September 2008.
|