City Projects: Utility System Improvements - Colleyville Boulevard /State Highway 26 Utility Relocation Phase I
Utility System Improvements
Colleyville Boulevard /State Highway 26
Utility Relocation Phase I
Key Information
- Relocation of existing water utility lines for the proposed widening of Colleyville Boulevard Phase I
Current Activity (as of September 2011)
- Municipal utility relocation plans complete
- Project has been substantially completed
Funding
- Project awarded at: $236,272
- Funding source:
- Utility Fund Available Cash Balance
Key Dates
- City Council award of contract to Champion Utility Construction: April 19, 2011
- Construction began: May 18, 2011
- Substantial construction was completed in August and the contractor is addressing final punch list items